Case 23-009185 • 4880 T Street, Sacramento CA • Card 32 of 55

The Notice and Order Named No Specific Permit; the Licensed Contractor Retained to Comply Refused the Undefined Permit and Walked Off

Risk: HIGH Punch: 9 / 10

1 — Header

The Notice and Order named no specific permit; the licensed contractor retained to comply refused the undefined permit and walked off.

In plain terms

When a city orders repairs on a building, it is supposed to say what work needs a permit. SCC §8.100.190 Here the city’s order and its violation list only said, in effect, “get all required permits” — without ever naming a single specific permit. M124 M125 To comply, the owner’s attorney brought in a licensed building contractor — Arthur Popov of Best of Remodel Inc., CSLB License #1040536 — who a month earlier had walked the whole property alongside two city inspectors. M036 When the attorney asked him to file the permit the city wanted, the contractor wrote back that everything on the list was already done, that he was being asked to pull a permit “for anything they ask” over loose “misc items” no one had put in writing, and that he was out. R.25-3549 The city’s own notes record the same thing twice — once saying the contractor “backed out,” M036 and again, days later, calling it the contractor’s “refusal to participate.” M037 That a detail this damaging shows up in the city’s file at all only came to light because the owner’s side forced the records out through public-records requests. R.26-1965

Bottom line: the city demanded permits but never said which ones, and the licensed contractor brought in to comply read the order, found the work done, and walked away rather than guess — a refusal the city wrote into its own file.
Source Citations (7)
  • M036Case note 09/16/2025 — on-site with PBI Bo Cosley; met contractor (Arthur Popov); handyman took care of “some of the violations”; 30 days to obtain building permit. Case note 10/20/2025 — contractor “backed out of the project”; permit application emailed. M036.pdf
  • M037Case note 10/23/2025 — Saakian to Lovato, “delay stems from contractor’s refusal to participate”; 11/21/2025 permit processed; 12/02/2025 permit issued, first itemized inspection list. M037.pdf
  • M124Notice and Order face page, 04/12/2023, Bo Cosley, Principal Building Inspector; “all required permits for repair shall be secured.” M124.pdf
  • M125Correction List — B31 “Other” and B59 SCC §8.100.190 “Permits Required” placeholder; no specific permit named. M125.pdf
  • R.25-3549Nov 2025 CPRA production; hosts the Saakian email thread (E.4) including Popov’s 10/20/2025 withdrawal message; closed as complete. NextRequest
  • R.26-1549Apr 2026 CPRA production; closed as complete. NextRequest
  • R.26-1965May 2026 searchable CitizenServe case file, 631 pages. Provenance source for M-page citations. NextRequest